Peak Cluster narrows carbon pipeline corridor to 100 metres and drops planned site near Chapel-en-le-Frith, as consultation opens

• Peak Cluster's further consultation on its carbon capture pipeline is now open and runs until 18 December.
• The company says the pipeline corridor has been cut from 300 metres to 100 metres wide in most places, and about 15% of the route has been revised.
• A planned above-ground installation known as the North Feeder, near Chapel-en-le-Frith, is no longer needed.
• The nearest drop-in event is at St Anne's Community Centre, Buxton, on 26 November, with a Derbyshire webinar on 1 December.
The scheme would collect carbon dioxide from cement and lime works in Derbyshire and Staffordshire, including the Hope works, and pipe it to storage beneath the East Irish Sea. Peak Cluster says it received more than 5,500 responses in its first consultation earlier this year, and that this feedback, along with technical studies and surveys, led to the changes. It now says the gas will travel at about 40 bar. A larger consultation on the wider design is planned for summer 2027. The Chronicle reported the dates of this consultation on 4 November; this update covers the changes now published.
Photo: Hope Cement Works seen from Bamford Edge. Peter McDermott / Geograph, CC BY-SA 2.0
Source: Peak Cluster; Derbyshire Live. Linked: Peak Cluster consultation.
Peak Cluster, the company behind a proposed carbon capture pipeline from Derbyshire and Staffordshire's cement and lime works, has opened a further public consultation, which runs from 12 November to 18 December 2026.
The scheme would capture carbon dioxide at cement and lime plants, including the Hope works in the Hope Valley, and carry it by underground pipeline through Cheshire and the Wirral for permanent storage beneath the East Irish Sea. Peak Cluster says Derbyshire and Staffordshire produce around 40% of the UK's cement and lime.
Reduced from 300 metres to 100 metres in most areas
According to the consultation website, the pipeline corridor has been reduced from 300 metres to 100 metres in most areas and around 15% of the route has been revised. The North Feeder above-ground installation, which was due to be built close to Chapel-en-le-Frith, is no longer needed. The company has also confirmed that carbon dioxide would be moved as a gas at an operating pressure of about 40 bar.
On the Wirral coast, planned compression facilities have been dropped. Peak Cluster says the remaining above-ground site there would be about 80 metres by 80 metres, with a vent stack of no more than 10 metres, down from 50 metres.
The North Feeder above-ground installation is no longer needed
The company says more than 5,500 people and organisations responded to its first consultation earlier this year. Chief executive David Parkin told Derbyshire Live that the changes had, in many cases, reduced the potential impact on local communities.
Derbyshire Live reports that the project has met some opposition from villages and residents along the route, and that Reform UK has said it would stop the scheme if elected to government.
Runs from 12 November to 18 December 2026
The nearest in-person event to the Hope Valley is at St Anne's Community Centre in Buxton on 26 November, and an online Derbyshire webinar is due on 1 December. Details and response forms are on the Peak Cluster consultation website. A further consultation on more detailed aspects of the project is planned for summer 2027.